Project management and Contract Administration Fill in the Blank

Fill in the blanks:
1. The first step in preparing an econometric model is to set up the ……………… and ……………… required.

Answer

Ans: columns, rows

2. The rows under the columns now deal in ……… with the factors already described to give the financial picture.

Answer

Ans: sequence

3. The areas of contingency, risk and sensitivity analysis are ………………….

Answer

Ans: interrelated

4. The analysis of average and maximum risk contingency provides an effective means of establishing …………….

Answer

Ans: sensitivity

5. In order to build a plant, an ………………… contractor must spend money at the proper rate to meet the required completion schedule.

Answer

Ans: Engineering & Construction (E&C)

6. ………………… in the early phases ahead of date development will lead to inefficient man hour utilization.

Answer

Ans: overstaffing

7. Once ………………. members are assigned from their functional departments, they become project oriented, reporting to the PM for their project execution functions.

Answer

Ans: project team

8. The ………………. manager presents the events leading to the project award.

Answer

Ans: commercial

9. The project construction manager prepares the construction plan during the ………………. phase.

Answer

Ans: project initiation

10. An approved bidders list is prepared reflecting the ………………. established in the procurement plan.

Answer

Ans: policies

11. The last stage in the development of the project schedule is to integrate the three independent sub- schedules to produce an overall ……………. schedule.

Answer

Ans: master project

12. In production design, these are ……………. and ……………. drawings.

Answer

Ans: piping, instrument drawings

13. A master project schedule developed by …………….. method provides realistic milestones.

Answer

Ans: top-down

14. …………….. will show up if material deliveries are ahead of the construction material required dates.

Answer

Ans: Float

15. The effectiveness of this system depends on continuous ……………….. and updating of the …………………

Answer

Ans: feedback

16. PERT/CPM or network analysis is a ……………….. system.

Answer

Ans: dynamic

17. …………….. of a network is to find out means to complete the project at an earlier time schedule than planned or reworked time while updating.

Answer

Ans: Crashing

18. Crashing can be achieved only by …………….. the time for activities yet to be done by employing additional resources with inevitable additional cost.

Answer

Ans: reducing

19. The ………………. number of starts and AFC issues can be entered and compared against the plan.

Answer

Ans: actual

20. ………………. is a symmetrical bell shaped curve traced by normal distribution.

Answer

Ans: Bell Curve

21. Project cost control starts on a wrong base if there is a …………………. estimate.

Answer

Ans: poor

22. Cost control can only be applied at a level corresponding to the quality and detail of the …………………. available.

Answer

Ans: estimate

23. The cost of commodities is set by …………….. and …………….. .

Answer

Ans: quality, quantity

24. …………….. addition is done through review and could lead to substantial cost saving of the project.

Answer

Ans: Economic value

25. The first step towards cost control is to prepare a …….. estimate for each discipline

Answer

Ans: man-hour

26. The initial field labour man-hour estimate is prepared in ……………. labour man-hours and then converted to the project labour man-hours.

Answer

Ans: standard

27. Every project has its unforeseens for which there must be a ……………….. .

Answer

Ans: contingency

28. The ……………….. to change must be applied equally firmly by all members of the project team.

Answer

Ans: resistance

29. Once agreement and approval have been reached about the vendor, call the vendor in for a …………….. meeting.

Answer

Ans: pre-commitment

30. Pre-award meetings should be held with short listed bidders prior to …………….. .

Answer

Ans: selection

31. A good project manager …………………. decisions made unilaterally by one group of the team without careful consideration of the effects on overall project costs, schedules and quality.

Answer

Ans: minimizes

32. A project manager, to achieve a successful project, must have a …………………. to induce progress.

Answer

Ans: stick

33. In general, …………….., …………….. and …………….. data is required as input by PM software.

Answer

Ans: Scheduling data, Cost/budget data, Resources data

34. Most of the ERP software provide …………….. architecture and PM software can be seamlessly integrated with ERP software.

Answer

Ans: open architecture

35. MS Project is a MS ………….. product.

Answer

Ans: Office

36. ……………. is the most commonly used PM software.

Answer

Ans: Primavera Project Planner (P3)

37. Engineering documentation these days is mainly kept in the ……………….. form.

Answer

Ans: electronic (soft) form

38. ……….. Centre is generally assigned the responsibility of storage/retrieval/issue of engineering documents.

Answer

Ans: Engineering Documentation

39. Many …………………. contracts include clauses that allow the contract to automatically renew if written notice is not provided before a defined period prior to the contract end date.

Answer

Ans: buy-side

40. Contracts on both the buy-side and sell-side frequently include provisions for …………………. if certain milestones are achieved, or …………………. charges if they are not.

Answer

Ans: cost reductions, penalty charges

41. ……………….. are used to manage financial information that is critical to meet the compliance regulations.

Answer

Ans: Contracts

42. Organizations that are not able to control their contracts are not able to control their …………….. .

Answer

Ans: businesses

43. ERP systems, while normally the central repository for large amounts of active and historical data, are often focused on ……………….. requirements.

Answer

Ans: back office

44. In any contract management implementation ERP system …………….. must be given serious consideration.

Answer

Ans: integration

45. Suppliers must go through some kind of official ……………… process before a commercial contract is awarded.

Answer

Ans: bid process

46. The ………………, an international standards body that oversees best practice in procurement, suggests that central procurement departments achieve their greatest effectiveness when they control more than 80% of an organization’s purchasing activity.

Answer

Ans: Chartered Institute of Purchasing and Supply

47. Although every sales person loves to close large deals, many sales people dislike the ………………. that accompanies the conclusion of these business dealings.

Answer

Ans: administration

48. Managing contracts is an ………………. responsibility.

Answer

Ans: enterprise

49. Most organizations …………….. key contract data into back-end systems.

Answer

Ans: manually

50. Contract negotiations between external parties often take place via …………….. .

Answer

Ans: e-mail

51. If your firm becomes known for its thorough and fair ………………, good suppliers will compete even more vigorously for your business.

Answer

Ans: contracting

52. Over time this will build a solid base of the most ……………… vendors with which you may work with greater confidence.

Answer

Ans: reliable

ed010d383e1f191bdb025d5985cc03fc?s=120&d=mm&r=g

DistPub Team

Distance Publisher (DistPub.com) provide project writing help from year 2007 and provide writing and editing help to hundreds student every year.