Management Book Objective Set Number 243

Q1: You are teaching a class of junior project leaders the benefit of calculating and understanding schedule variance(SV).Your class is using the following value to determine the ‘health’ of project. PV=USD220,000 EV= 200,000, AC=280,000.According to your analysis the SV and hence the status of the project is AnswerAnswer: -USD20,000 the project is behind schedule Q2:…