Software project management mcq set 2

Q41: The final form of testing COTS software is___testing

  • A. Unit
  • B. Integration
  • C. Alpha
  • D. Module
  • E. Beta
Answer

Answer E. Beta

Q42: Which of the following items should not be included in the software project management plan?

  • A. The techniques and case tools to be used
  • B. Detailed schedules, budgets and resource allocations
  • C. The life cycle model to be used
  • D. The organisational structure of the development organisation, project responsibilities, managerial objectives and priorities
  • E. None of the above
Answer

Answer E. None of the above

Q43: An example of the risk involved in software development is

  • A. Key personnel may resign before the product is complete
  • B. The manufacturer of critical components (e.g. the hardware associated with a real-time system) may go bankrupt
  • C. Technology changes may render the product obsolete
  • D. Competitors may market a fully functional lower-cost equivalent package
  • E. All of these are risks involved in software development
Answer

Answer E. All of these are risks involved in software development

Q44: Software Science bases its estimation of the size of a product on

  • A. Files (Fi), Flows (Fl) and Processes (Pr)
  • B. Lines of Code (kLOC)
  • C. Function Points (FP)
  • D. operands and operators
  • E. Feature Points (FeP)
Answer

Answer D. operands and operators

Q45: Work that continues throughout the project and does not relate to any specific phase of software development is termed a(n)

  • A. Milestone
  • B. Project function
  • C. Activity
  • D. Task
  • E. Baseline
Answer

Answer B. Project function

Q46: The advantage of following the IEEE Standard for drawing up a Software Project Management Plan (SPMP) – see IEEE Standard 1059.1 1987 – is

  • A. It is drawn up by representatives from major software development organisations
  • B. It is designed for all types of software products
  • C. It is a framework that can be used irrespective of process model or specific techniques
  • D. It can be tailored for each organisation for a particular application area, development team or technique
  • E. All of the above
Answer

Answer E. All of the above

Q47: The best way to test the Software Project Management Plan (SPMP) is by

  • A. Prototyping
  • B. Inspection
  • C. Simulation
  • D. Compilation
  • E. Debugging
Answer

Answer B. Inspection

Q48: The aim of software engineering is to produce software that is

  • A. Fault-free
  • B. Delivered on time
  • C. Delivered within budget
  • D. Satisfies users’ needs
  • E. All of these are the aims of software engineering
Answer

Answer E. All of these are the aims of software engineering

Q49: A simple way of looking at the spiral software life-cycle model is as a waterfall model with each phase proceeded by

  • A. Build-and-fix
  • B. Freezing
  • C. Synchronization
  • D. Testing
  • E. Risk analysis
Answer

Answer E. Risk analysis

Q50: Which of the following is not a phase of project management?

  • A. Project planning
  • B. Project scheduling
  • C. Project controlling
  • D. Project being
Answer

Answer D. Project being

Q51: Who introduced the bar charts?

  • A. Williams henry
  • B. Henry Gantt
  • C. Jane Gantt
  • D. Joseph henry
Answer

Answer B. Henry Gantt

Q52: Bar charts were modified later to obtain the milestone charts

  • A. True
  • B. False
Answer

Answer A. True

Q53: The full form of PERT is___

  • A. Program Evaluation and Rate Technology
  • B. Program Evaluation and Robot Technique
  • C. Program Evaluation and Robot Technology
  • D. Program Evaluation and Review Technique
Answer

Answer D. Program Evaluation and Review Technique

Q54: The full form of CPM is___

  • A. Critical Path Method
  • B. Control Path Method
  • C. Critical Plan Management
  • D. Control Path Management
Answer

Answer A. Critical Path Method

Q55: In bar charts, which colour is used to show the actual progress?

  • A. Red
  • B. Black
  • C. Blue
  • D. Green
Answer

Answer D. Green

Q56: A PERT network is activity-oriented while a CPM network is eventoriented

  • A. True
  • B. False
Answer

Answer A. True

Q57: ___are used to represent activity in a network diagram

  • A. Circles
  • B. Squares
  • C. Rectangles
  • D. Arrows
Answer

Answer D. Arrows

Q58: The shortest possible time in which an activity can be achieved under ideal circumstances is known as___

  • A. Pessimistic time estimate
  • B. Optimistic time estimate
  • C. Expected time estimate
  • D. The most likely time estimate
Answer

Answer B. Optimistic time estimate

Q59: According to the time estimates made by the PERT planners, the maximum time that would be needed to complete an activity is called as___

  • A. The most likely time estimate
  • B. Optimistic time estimate
  • C. Pessimistic time estimate
  • D. Expected time estimate
Answer

Answer C. Pessimistic time estimate

Q60: In a network, a critical path is the time-wise shortest path

  • A. True
  • B. False
Answer

Answer B. False

Q61: The difference between the maximum time available and the actual time needed to perform an activity is known as___

  • A. Free float
  • B. Independent float
  • C. Total float
  • D. Half float
Answer

Answer C. Total float

Q62: Network Diagrams are a___of the activities of a given project

  • A. graphical representation
  • B. statistical representation
  • C. mathematical representation
  • D. none of the above
Answer

Answer A. graphical representation

Q63: Activities drawn in a___in a network diagram

  • A. imaginary activity
  • B. random relationship
  • C. serial relationship
  • D. none of the above
Answer

Answer C. serial relationship

Q64: A Dummy activity is an activity which does not require a___

  • A. time or resource
  • B. imaginary activity
  • C. dependence
  • D. operations in the diagram
Answer

Answer A. time or resource

Q65: The best way to generate the WBS is as part of the___session

  • A. Joint Project Planning
  • B. decomposition
  • C. completion
  • D. Project Overview Statement
Answer

Answer A. Joint Project Planning

Q66: The technique for generating the WBS will___even the most complex project to a set of clearly defined activities

  • A. document
  • B. reduce
  • C. guide
  • D. all the above
Answer

Answer B. reduce

Q67: Once the team is satisfied it has completed the activity list for the firstlevel breakdown, the members are___

  • A. finished
  • B. reported
  • C. Joined
  • D. all the above
Answer

Answer A. finished

Q68: Which of these is not a cause of project failure?

  • A. Improper Planning
  • B. Poor weather condition
  • C. Lack of technical skills
  • D. Defective structural design
Answer

Answer B. Poor weather condition

Q69: A construction schedule is prepared after collecting

  • A. Number of operations
  • B. Output of Labour and Machinery
  • C. Quantity of various items
  • D. All the above
Answer

Answer D. All the above

Q70: In the time-cost optimization, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having

  • A. Longest duration
  • B. Highest cost slope
  • C. Least cost slope
  • D. Shortest duration
Answer

Answer C. Least cost slope

Q71: Which qualities should a good project manager posse?

  • A. Leadership
  • B. Intigrity
  • C. Knowledge of Construction
  • D. All of the above
Answer

Answer D. All of the above

Q72: Construction Manager should have___skills

  • A. Technical Skills
  • B. Conceptual Skills
  • C. Adaptability
  • D. All of the above
Answer

Answer D. All of the above

Q73: Low cost, higher volume items requires

  • A. no inspection
  • B. little inspection
  • C. intensive inspection
  • D. 100% inspection
Answer

Answer B. little inspection

Q74: High cost, low volume items requires

  • A. no inspection
  • B. little inspection
  • C. intensive inspection
  • D. 100% inspection
Answer

Answer C. intensive inspection

Q75: The mean of sampling distribution is

  • A. less than mean of process distribution
  • B. more than mean of process distribution
  • C. equal to mean of process distribution
  • D. any of the above
Answer

Answer C. equal to mean of process distribution

Q76: The percent of the sample means will have values that are within +-3 standard deviations of the distribution mean is

  • A. 95.5
  • B. 96.7
  • C. 97.6
  • D. 99.7
Answer

Answer D. 99.7

Q77: The dividing lines between random and non random deviations from mean of the distribution are known as

  • A. upper control limit
  • B. lower control limit
  • C. control limits
  • D. two sigma limits
Answer

Answer C. control limits

Q78: The chart used to monitor variable is

  • A. Range chart
  • B. p-chart
  • C. c-chart
  • D. All of the above
Answer

Answer A. Range chart

Q79: The chart used to monitor attributes is

  • A. Range chart
  • B. Mean chart
  • C. p-chart
  • D. All of the above
Answer

Answer C. p-chart

Q80: Central tendency of a process is monitored in

  • A. Range chart
  • B. Mean chart
  • C. p-chart
  • D. c-chart
Answer

Answer B. Mean chart

ed010d383e1f191bdb025d5985cc03fc?s=120&d=mm&r=g

DistPub Team

Distance Publisher (DistPub.com) provide project writing help from year 2007 and provide writing and editing help to hundreds student every year.