QN1. Which of the following is not a characteristic of a production system
a) It is a universally applicable model
b) Varies from enterprise to enterprise
c) It is a framework within which production activities take place
d) Ensures coordination of various production operations
Answer: a) It is a universally applicable modelAnswer
QN2. Which of the following is not a type of production system
a) Continuous production
b) Job or unit production
c) Intermittent production
d) Flexible manufacturing
Answer: c) Intermittent productionAnswer
QN3. All of the following are production functions except
a) Aggregate planning
b) Pricing of products
c) Capacity assessment
d) Scheduling of operations
Answer: b) Pricing of productsAnswer
QN4. Order winner means
a) The sales person who gets the order
b) The factor of the product that wins the order for the firm
c) Order that results in high profits
d) Repeat order
Answer: c) Order that results in high profitsAnswer
QN5. All of the following are functions of forecasting except
a) An estimation tool
b) A tool for predicting events related to operations planning and control
c) An input for the JIT system
d) A vital prerequisite for the planning process
Answer: c) An input for the JIT systemAnswer
QN6. Degree of uncertainty in short term forecasting is
a) High
b) Low
c) Nil
d) Significant
Answer: a) High Answer
QN7. All of the following are key areas of forecasting except
a) Better materials management
b) Rationalized manpower decisions
c) Basis for planning and scheduling
d) Routine decisions
Answer: b) Rationalized manpower decisionsAnswer
QN8. Which of the following is a dependent demand for an organization manufacturing refrigerators
a) Compressor
b) Requirement for a DG set
c) Refrigerators
d) Tea coffee vending machine
Answer: b) Requirement for a DG setAnswer
QN9. If a forecast repeatedly overestimates actual demand, bias will have
a) Positive value
b) Negative value
c) Zero value
d) Infinity
Answer: a) Positive valueAnswer
QN10. Which of the following is not a qualitative method of forecasting
a) Delphi method
b) Historical data
c) Econometric models
d) Nominal group technique
Answer: a) Delphi methodAnswer
QN11. The most suitable method for forecasting the demand for a brand new product is
a) Moving averages
b) Historical data
c) Exponential smoothening
d) Delphi method
Answer: c) Exponential smootheningAnswer
QN12. The planning that addresses the supply side of a firm’s ability to meet the demand is known as
a) Business plan
b) Aggregate production planning
c) Aggregate capacity planning
d) Master production scheduling
Answer: b) Aggregate production planningAnswer
QN13. Which of the following is not a considerations in developing an aggregate production plan
a) Concept of aggregation
b) Goal for aggregate planning
c) Forecast of aggregate demand
d) Supplier lead time
Answer: c) Forecast of aggregate demandAnswer
QN14. The aggregate production planning strategy that cannot be employed in a strong union environment is
a) Changing inventory levels
b) Changing workforce levels
c) Subcontracting
d) Influencing demand
Answer: c) SubcontractingAnswer
QN15. Which of the following is not an alternative for managing supply
a) Inventory based alternatives
b) Promotional schemes
c) Capacity adjustment
d) Capacity augmentation
Answer: d) Capacity augmentationAnswer
QN16. All of the following are capacity adjustment alternatives except
a) Hiring/ Firing of workers
b) Varying shifts
c) Varying working hours
d) Subcontracting
Answer: d) SubcontractingAnswer
QN17. Which of the following is not an aggregate production planning method
a) Trial-and-error method
b) Transportation method
c) Linear programming method
d) Assignment method
Answer: d) Assignment methodAnswer
QN18. All of the following are characteristics of Master Production Scheduling except
a) MPS makes use of actual customer orders
b) Product varieties are taken care of in MPS
c) MPS is a critical linkage between planning and execution of operations
d) It is same as rough cut capacity planning
Answer: d) It is same as rough cut capacity planningAnswer
QN19. Which is not a characteristic of a Bill Of Materials
a) List all parts required for one unit of a product
b) Shows dependency relationships
c) Gives total number of a part used in a product
d) Indicates multi levels of a product
Answer: c) Gives total number of a part used in a productAnswer
QN20. All of the following are time phasing requirement of an MRP logic except
a) Gross requirement will occur at the middle of a period
b) On hand inventory will be measured at the end of a period
c) Planned order release will occur at the beginning of a period
d) Lead time considerations are not taken for time phasing
Answer: d) Lead time considerations are not taken for time phasingAnswer
QN21. Which of the following is not an input to the MRP system
a) The Master Production Schedule
b) Bill of materials
c) Engineering drawing
d) Inventory status file
Answer: c) Engineering drawingAnswer
QN22. Which of the following is not a Lot sizing technique
a) The lot-for lot technique
b) The EOQ approach
c) Mini-Max approach
d) Period order quantity approach
Answer: c) Mini-Max approachAnswer
QN23. The process of tracing the effect of one component in another is called
a) Pegging
b) Cycle counting
c) Lot sizing
d) Time fencing
Answer: d) Time fencingAnswer
QN24. Stability in an MRP is achieved by
a) Updating
b) Cycle counting
c) Lot Sizing
d) Time fencing
Answer: a) UpdatingAnswer
QN25. Time fence means
a) The shortest lead-time from raw material to finished production of an item
b) Ensuring accuracy of inventory records
c) Method used to update MRP at regular intervals
d) Calculating net requirements of components
Answer: a) The shortest lead-time from raw material to finished production of an itemAnswer
QN26. All of the following are characteristics of capacity except
a) It is the maximum rate at which a system can accomplish work
b) Capacity depends on the bottleneck
c) Capacity is the productive capability of a facility
d) Capacity is measured in monetary terms
Answer: b) Capacity depends on the bottleneckAnswer
QN27. Operations managers are concerned with capacity for several reasons. Which of the following is not a concern
a) Enough capacity to meet customer demands
b) Capacity affects cost efficiency of operations
c) Investment required in capacity
d) Machine locations in a facility
Answer: c) Investment required in capacityAnswer
QN28. Which of the following is not a short term strategy for modifying capacity
a) Inventories
b) Employment levels
c) Subcontracting
d) Expansion
Answer: d) ExpansionAnswer
QN29. All of the following are steps in capacity control except
a) Monitoring of output
b) Comparing with capacity plan
c) Assessing demand
d) Taking corrective actions
Answer: d) Taking corrective actionsAnswer
QN30. Multi-skilling of work force doesn’t results in
a) Increasing capacity
b) Increasing flexibility
c) Improving productivity
d) Waste elimination
Answer: c) Improving productivityAnswer
QN31. Activity not associated with Dispatching is
a) Issue of instructions concerning movement of materials between work centers
b) Issue of instructions to operators
c) Loading work centers with jobs
d) Issue instructions concerning the issue and return of special tools
Answer: b) Issue of instructions to operatorsAnswer
QN32. Routing doesn’t include
a) Sequence of processes, operations for a product
b) Machines, tools, work stations used in producing the product
c) Standard time applicable for each operation
d) Detailed skills of the operator for each operation
Answer: d) Detailed skills of the operator for each operationAnswer
QN33. Three planning premises are used in production management. Which of the following is not one among them
a) Make to stock
b) Make to order
c) Assemble to order
d) Make subassemblies
Answer: d) Make subassembliesAnswer
QN34. A strategy that is not used for altering lead time is
a) Overlapping
b) Lot sizing
c) Operations splitting
d) Lot splitting
Answer: b) Lot sizingAnswer
QN35. Backlogs can be reduced by all of the following except
a) Increasing work center capacity
b) Reducing order release rate
c) Increasing lead time
d) Subcontracting
Answer: c) Increasing lead timeAnswer
QN36. Priority index in scheduling is also known as
a) Critical ratio
b) Critical Path
c) Random number
d) Earliest due date
Answer: b) Critical PathAnswer
QN37. All of the following are characteristics of flow shop production except
a) Special purpose equipment
b) Many number of end items
c) Low skilled workers
d) Low in process inventories
Answer: b) Many number of end itemsAnswer
QN38. Which of the following is not a characteristic of job shop production
a) Multipurpose equipment
b) Highly skilled workers
c) High investment
d) Low raw material inventory
Answer: d) Low raw material inventoryAnswer
QN39. Bottleneck operation in line balancing means
a) Having high operation time
b) Having high cycle time
c) Having low operation time
d) Having more no. of follower operations
Answer: d) Having more no. of follower operationsAnswer
QN40. Which of the following is not associated with line balancing
a) Precedence diagrams
b) Cycle time
c) Closeness matrix
d) Minimum number of workstations
Answer: d) Minimum number of workstationsAnswer