QN1. If the order winner is delivery speed to customer, then the production planning and control system must focus on:
a) Cost
b) Lead time
c) Quality
d) Coordination with Marketing
Answer: b) Lead timeAnswer
QN2. A firm uses simple exponential smoothing to forecast demand with a = 0.2. The forecast for the month of March was 500 units whereas the actual demand turned out to be 460 units. What is the forecast for the month of April?
a) 489.6
b) 492
c) 480
d) 490
Answer: b) 492Answer
QN3. Bias as a measure of forecast error is used to determine:
a) The total magnitude of error
b) The direction of error
c) Absolute value
d) Weighted average
Answer: c) Absolute valueAnswer
QN4. Aggregate output planning generally consists of planning a desired output over a period of:
a) one week
b) five years
c) daily
d) three months to 1 year
Answer: d) three months to 1 yearAnswer
QN5. Optimum inventory level as per EOQ system will increase:
a) in direct proportion to increase in holding cost
b) inversely with setup cost
c) in proportion to square root of demand for the year
d) in direct proportion to square root of holding cost
Answer: a) in direct proportion to increase in holding costAnswer
QN6. Product structure tree is:
a) diagram explaining the features of a product
b) used to display the total makeup of a particular product
c) is representation of a tree
d) identical to decision tree
Answer: a) diagram explaining the features of a productAnswer
QN7. Kit numbers are used in MPS:
a) when there are many small, loose parts – such as fasteners, nuts and bolts – at level 1 in the product structure
b) to identify related items
c) to add complexity to planning
d) as a quick aid to forecasting
Answer: a) when there are many small, loose parts – such as fasteners, nuts and bolts – at level 1 in the product structureAnswer
QN8. MRP takes the output from the master schedule, combines that with information from inventory
records and product structure records and determines:
a) the volume of production in each period
b) the schedule of timing and quantities for each item to get the right materials to the right place at the right time
c) closing inventory
d) whether customer demand can be met
Answer: b) the schedule of timing and quantities for each item to get the right materials to the right place at the right timeAnswer
QN9. Manufacturing Resource Planning is:
a) the planning of resources in the manufacturing environment using the closed loop system
b) another term for rough cut capacity planning
c) is also known as MRP I or little
d) is a quicker way to MRP
Answer: a) the planning of resources in the manufacturing environment using the closed loop systemAnswer
QN10. A classification system has been devised to determine how well an MRP system has been
implemented. Class C company is:
a) one which has MRP II in full use and the closed loop is working
b) one in which MRP system is working only in the computing department
c) one which may have MRP, capacity planning and shop floor controls working
d) one which uses MRP for inventory ordering but not for scheduling
Answer: d) one which uses MRP for inventory ordering but not for schedulingAnswer
QN11. MRP logic uses the following relationships:
a) Net requirements = total requirements – available inventory
b) Net requirements = scheduled receipts + inventory on hand
c) Net requirements = gross requirements – allocations
d) Net requirements = gross requirements – on hand inventory
Answer: a) Net requirements = total requirements – available inventoryAnswer
QN12. Lot-for-Lot technique in MRP yields:
a) high holding cost
b) low setup cost
c) zero holding cost
d) zero setup cost
Answer: c) zero holding costAnswer
QN13. The simulation studies on many of the lot sizing rules show:
a) good performance of L-4-L rule
b) good performance of EOQ rule
c) poor performance of PPB, GR and MCP rules
d) poor performance of L-4-L and EOQ rules
Answer: b) good performance of EOQ ruleAnswer
QN14. Time fence is a designated length of time
a) to create system nervousness in MRP system
b) that is the longest lead time from raw material to finished production for an end item
c) that must pass without changing the MPS, to stabilise the MRP system; afterward the MPS is allowed to change
d) around which the system is upgraded
Answer: c) that must pass without changing the MPS, to stabilise the MRP system; afterward the MPS is allowed to changeAnswer
QN15. Pegging is used in MRP system for:
a) identifying which components are affected by disruptions in material plans
b) pausing the system
c) showing old records
d) showing current records with updated status
Answer: a) identifying which components are affected by disruptions in material plansAnswer
QN16. Route sheet used in production planning and control is:
a) used to indicate the location of each department
b) a document to show the routing of a component, including the work centers and operation times, through its production processes
c) a flow process chart used for process change
d) a document showing the daily production schedule
Answer: b) a document to show the routing of a component, including the work centers and operation times, through its production processesAnswer
QN17. The Master Production Schedule (MPS) is a schedule of:
a) weekly production plan for each product according to customer orders and demand forecasts
b) aggregate production plan in product groups
c) daily production plan for shop floor control
d) business activity expressed in money value
Answer: b) aggregate production plan in product groupsAnswer
QN18. A good strategy to meet short term overload for a month can be:
a) buy a new equipment
b) invest in a new project
c) subcontract work
d) telling marketing that the job cannot be done
Answer: c) subcontract workAnswer
QN19. Infinite loading is:
a) assigning jobs to work centers without considering the work center’s capacity
b) using Gantt chart for loading
c) using visual load profile for showing load
d) considering loading of planned orders only
Answer: a) assigning jobs to work centers without considering the work center’s capacityAnswer
QN20. Final Assembly Schedule can serve as MPS:
a) when the number of end products manufactured is small
b) when the number of end products is large
c) when there is a need to disaggregate
d) when M-bills have to be used
Answer: a) when the number of end products manufactured is smallAnswer
QN21. An aluminium extruder forecasted the demand for pipe extrusions to be 500 units per month
for each of three months. The actual demands turned out to be 400, 560 and 700. The forecast
error in terms of MAD(Mean Absolute Deviation) is:
a) -50 units
b) 125 units
c) 120 units
d) 53 units
Answer: d) 53 unitsAnswer
QN22. Frigerware has experienced demand for ice coolers at 400 units for April, 500 units for May and
600 units for June. The forecast of demand for July using a three period model with the most
recent period’s demand weighted twice as heavily as each of the previous two period’s demand
is:
a) 425
b) 525
c) 625
d) 400
Answer: b) 525Answer
QN23. In the regression model for forecasting, the forecast of the period’s demand F is expressed as
F = a + bX, where:
a) F is the independent variable
b) X is the dependent variable
c) X is the independent variable
d) a is the slope of the line
Answer: F = a + bX, where:Answer
QN24. Capacity is a facility’s productive capability, usually expressed as volume of:
a) input in case of automobiles
b) output in case of steel producer
c) likely business as per marketing
d) output in case of hospital
Answer: b) output in case of steel producerAnswer
QN25. For short term periods of up to one year, fundamental capacity is fixed. However, short term
adjustments of capacity are possible by:
a) building inventories during slack periods to meet later demand
b) subcontracting during slack periods
c) building inventories during peak periods to meet demand in slack periods
d) wishing that some customers may cancel the order
Answer: a) building inventories during slack periods to meet later demandAnswer
QN26. Steel manufacturing is an example of :
a) Job manufacturing process
b) Continuous manufacturing flow process
c) Assembly line process
d) None of the above
Answer: b) Continuous manufacturing flow processAnswer
QN27. Visual Load profile is:
a) a graph comparing work loads and capacities on a time scale
b) identical to Gantt load chart
c) used for forward scheduling process
d) used for job sequencing
Answer: a) a graph comparing work loads and capacities on a time scaleAnswer
QN28. SPT rule in scheduling:
a) assigns highest priority to the slowest job
b) prioritises on basis of setup time
c) prioritises on basis of delivery times
d) assigns highest priority to the job order whose processing time is shortest
Answer: c) prioritises on basis of delivery timesAnswer
QN29. Which sequencing rule will you prefer for minimising average job lateness:
a) Shortest processing time rule
b) Longest processing time rule
c) Earliest Due Date rule
d) First cum first served rule
Answer: c) Earliest Due Date ruleAnswer
QN30. For scheduling N jobs through two machine centers in series, you will use:
a) Johnson rule to decide the sequence and then schedule on a Gantt chart
b) McLaren’s Order Moment
c) Groff’s Algorithm
d) None of the above
Answer: a) Johnson rule to decide the sequence and then schedule on a Gantt chartAnswer
QN31. If a machining center has a machine utilisation of 95% and operator efficiency of 80%, what is
the effective work centre capacity in July assuming 26 working days and 3 shifts running each
day:
a) 472.24 hours
b) 472 hours
c) 158.08 hours
d) 59.28 hours
Answer: a) 472.24 hoursAnswer
QN32. Critical Ratio used in Capacity Planning and Control is:
a) Time to due date divided by required time for remaining operations
b) Time for first job divided by time for second job
c) Capacity consumed by the job divided by total capacity of the plant
d) Capacity of output divided by capacity of input
Answer: a) Time to due date divided by required time for remaining operationsAnswer
QN33. Job A and B are waiting to be released. Both will go to work center 1. Then A will continue on
to work center 3 while B will go to work center 4. Suppose that A has high priority on the first
work center and center 4 is backlogged and center 4 is idle. Which order should be released
first?
a) Job A
b) Job B
c) Both Job A and Job B together
d) Toss a coin and if its heads, go for Job A otherwise Job B.
Answer: a) Job AAnswer
QN34. Cycle time as used in assembly line manufacturing is:
a) the time taken in last work station
b) the productive time divided by demand
c) the time taken by the bottleneck operation
d) both b) and c) are considered and the higher value taken
Answer: b) the productive time divided by demandAnswer
QN35. In an assembly line the total processing time per, unit is 380 seconds, and the cycle time for
the line is 90 seconds. What is the minimum number of workstations required in the assembly
line?
a) 4 stations
b) 4.22 stations
c) 5 stations
d) 4.2 stations
Answer: a) 4 stationsAnswer
QN36. Runout Time (ROT) used in batch processing is:
a) the time taken to complete the batch
b) the current inventory of an item divided by the demand per period for that item
c) the demand for the item divided by the opening inventory level
d) time for setup plus processing time
Answer: b) the current inventory of an item divided by the demand per period for that itemAnswer
QN37. JIT is:
a) another management jargon
b) a philosophy of waste reduction and techniques for reducing inventory and waste
c) applicable only to job shop units
d) none of the above
Answer: b) a philosophy of waste reduction and techniques for reducing inventory and wasteAnswer
QN38. If the setup cost is Rs 10,000 per setup, annual demand is 100,000 units and holding cost is Rs
200 per unit per year the optimal batch quantity in production should be (rounded off):
a) 3162
b) 316
c) 31623
d) 3000
Answer: a) 3162Answer
QN39. Kanban is:
a) a push production system
b) another word for MRP system
c) a pull system based on a ‘visible record’ or ‘card’
d) input output system
Answer: a) a push production systemAnswer
QN40. If D is the demand per unit of time, L is the lead time, A is the container capacity and S the
safety stock factor, the number of Kanbans N will be :
a) DL(1+S)/A
b) A(l+S)/D
c) LAS(l + D)/24
d) (D/A) + L+S
Answer: a) DL(1+S)/AAnswer