Management science mcq set 5

161. Which of the following is true with regard to a Linear Programming Model?
A. No guarantee to get integer valued solution
B. The relationship among decision variables is liner
C. Both a and b
D. None of the these

Answer

D. None of the these

162. The graphical method if LPP uses:
A. Linear equations
B. Constraint equations
C. Objective function
D. All of the above

Answer

D. All of the above

163. Constraints in an LPP are treated as active, if they:
A. Do not consume all the available resources at optimality
B. Represent optimal solution
C. Both a and b
D. None of these

Answer

B. Represent optimal solution

164. While solving a LPP graphically, the area bounded by constraints is called ___. .
A. Feasible region
B. Infeasible region
C. Unbounded region
D. None of these

Answer

A. Feasible region

165. While solving an LPP, infeasibility may be removed by:
A. Removing a variable
B. Removing a constraint
C. Adding a variable
D. Adding a constraint

Answer

B. Removing a constraint

166. ___. variables are fictitious and cannot have any physical meaning.
A. Slack variables
B. Surplus variables
C. Artificial variables
D. Decision variables

Answer

C. Artificial variables

167. An optimal solution is considered as the ___ among the feasible solutions.
A. Worst
B. Best
C. Ineffective
D. None of these

Answer

B. Best

168. ___ method is used to solve an assignment problem.
A. American method
B. Hungarian method
C. German method
D. British method

Answer

B. Hungarian method

169. The allocated cells in the transportation table are called ___ ___.
A. Occupied cells
B. Empty cells
C. Unoccupied cells
D. None of these

Answer

A. Occupied cells

170. In transportation Problems, VAM stands for ___. .
A. Value Addition Method
B. Vogel’s Approximation Method
C. Virgenean Approximation Method
D. None of these

Answer

B. Vogel’s Approximation Method

171. Initial feasible solution to a transportation Problem can be found out by ___. .
A. VAM
B. MODI Method
C. Both a and b
D. None of these

Answer

A. VAM

172. ___. is applied to determine optimal solution.
A. NWCR
B. VAM
C. MODI Method
D. None of these

Answer

C. MODI Method

173. A Transportation Problem is said to be unbalanced when total supply is not equal to ___.
A. Total cost
B. Total demand
C. Both a and b
D. None of these

Answer

B. Total demand

174. For a minimisation Transportation Problem, the objective is to minimise:
A. Profit
B. Cost
C. Solution
D. None of these

Answer

B. Cost

175. ___ is an important Operations Research Technique to analyse the queuing behaviour.
A. Game theory
B. Waiting line theory
C. Decision theory
D. Simulation

Answer

B. Waiting line theory

176. An organisation chart is an example of ___
A. Iconic model
B. Mathematical model
C. Analogue model
D. None of these

Answer

C. Analogue model

177. ___. model is a map which indicates roads, highways, towns and inter-relationships
A. Iconic model
B. Analogue model
C. Mathematical model
D. None of these

Answer

B. Analogue model

178. Operations Research techniques help to find ___ solution.
A. Feasible solution
B. Infeasible solution
C. Optimal solution
D. None of these

Answer

C. Optimal solution

179. Operations Research Techniques involves ___ approach.
A. Team approach
B. Critical approach
C. Individual approach
D. None of these

Answer

C. Individual approach

180. A LPP model doesnot contain:
A. Decision
B. Constraints
C. Feasible solution
D. Spread Sheet

Answer

D. Spread Sheet

181. Straight lines shown in a linear programming graph indicates ___
A. Objective function
B. Constraints
C. Points
D. All of the above

Answer

B. Constraints

182. Non-negativity constraints are written as ___
A. Equality
B. Non-equality
C. Greater than or equal to
D. Less than or equal to

Answer

C. Greater than or equal to

183. PERT stand for:
A. Performance Evaluation Review Technique
B. Programme Evaluation Review Technique
C. Programme Evaluation Research Technique
D. None of these

Answer

B. Programme Evaluation Review Technique

184. An activity which must be completed before commencement of one or more other activities iscalled ___ ___
A. Successor activity
B. Predecessor activity
C. Dummy activity
D. None of these

Answer

B. Predecessor activity

185. In network diagram, events are commonly represented by ___. .
A. Arrows
B. Nodes
C. Triangles
D. None of these

Answer

B. Nodes

186. ___. . is activity oriented network diagram.
A. CPM
B. PERT
C. Histogram
D. Ogive

Answer

A. CPM

187. ___ is an event oriented network diagram.
A. CPM
B. PERT
C. Histogram
D. Ogive

Answer

B. PERT

188. An activity which does not consume either resource or time is called ___ ___
A. Predecessor activity
B. Successor activity
C. Dummy activity
D. Terminal activity

Answer

C. Dummy activity

189. ___. . is a series of activities related to a project.
A. Network
B. Transportation Model
C. Assignment model
D. None of these

Answer

A. Network

190. An event which represents the beginning of more than one activity is a :
A. Merge event
B. Net event
C. Burst event
D. None of these

Answer

C. Burst event

191. Activities lying on critical path are called ___ ___
A. Critical activities
B. Non-critical activities
C. Dummy activities
D. None of these

Answer

A. Critical activities

192. Activities that cannot be started until one or more of the other activities are completed, arecalled ___
A. Dummy activities
B. Initial activities
C. Successor activities
D. Predecessor activities

Answer

C. Successor activities

193. ___ ___ is the sequence of activities which determines the total project duration.
A. Critical path
B. Network
C. Non-critical activities
D. None of these

Answer

A. Critical path

194. PERT emphasises on ___
A. Activity
B. Time
C. Cost
D. None of these

Answer

B. Time

195. ___ is the duration by which an activity can be delayed without delaying the completionof the project.
A. Earliest Start Time
B. Earliest Finish Time
C. Latest Start Time
D. Latest Finish Time

Answer

C. Latest Start Time

196. The EST + activity duration = ___ ___.
A. Earliest Finish Time
B. Latest Start Time
C. Latest Finish Time
D. None of these

Answer

A. Earliest Finish Time

197. ___ ___ is the latest time by which an activity can be finished without delaying thecompletion of the project.
A. LST
B. LFT
C. EFT
D. EST

Answer

B. LFT

198. ___. . is a scheme or design of something intended to do.
A. Network
B. Float
C. Project
D. Program

Answer

A. Network

199. In a network diagram, activity is denoted by ___ ___
A. Node
B. Arrow
C. Triangle
D. None of these

Answer

B. Arrow

200. ___ is the duration by which an activity can be delayed without delaying the project.
A. Slack
B. Total float
C. Both a and b
D. None of these

Answer

B. Total float

ed010d383e1f191bdb025d5985cc03fc?s=120&d=mm&r=g

DistPub Team

Distance Publisher (DistPub.com) provide project writing help from year 2007 and provide writing and editing help to hundreds student every year.