Information systems management mcq set 5

Q161: Decision making model was proposed by___

Answer option

  • A. Harry Goode
  • B. Herbert A Simon
  • C. Recon Michal
  • D. None of this
Answer

Answer B. Herbert A Simon

Q162: A context diagram

Answer option

  • A. Describes the context of a system
  • B. is a DFD which gives an overview of the system
  • C. is a detailed description of a system
  • D. is not used in drawing a detailed DFD
Answer

Answer B. is a DFD which gives an overview of the system

Q163: A manager and the head of engineering discuss a change to a major work package. After the meeting, the manager contacts you and tells you to complete the paperwork to make the change. This is an example of:

Answer option

  • A. Management attention to scope management
  • B. Management planning
  • C. A project expediter position
  • D. A change control system
Answer

Answer C. A project expediter position.

Q164: Which of the following processes has the Risk Register as the primary output?

Answer option

  • A. Perform Qualitative Risk Analysis
  • B. Monitor and Control Risks
  • C. Plan Risk Management
  • D. Identify Risks
Answer

Answer D. Identify Risks

Q165: A risk response which involves eliminating a threat is called:

Answer option

  • A. Mitigation
  • B. Deflection
  • C. Avoidance
  • D. b and d
Answer

Answer A. Mitigation

Q166: An example of risk mitigation is:

Answer option

  • A. Using proven technology in the development of a product to lessen the probability that the product will not work
  • B. Purchasing insurance
  • C. Accepting a lower profit if costs overrun
  • D. a and b
Answer

Answer D. a and b

Q167: Mitigating risk could involve

Answer option

  • A. identifying risks, obtaining insurance and developing alternatives
  • B. contracting and quality assurance
  • C. developing standards, buying insurance, and planning for contingencies and
  • D. re-scoping the project and reassessing requirements
Answer

Answer D. re-scoping the project and reassessing requirements

Q168: The linear sequential model of software development is

Answer option

  • A. A reasonable approach when requirements are well defined
  • B. A good approach when a working program is required quickly
  • C. The best approach to use for projects with large development teams
  • D. An old-fashioned model that cannot be used in a modern context
Answer

Answer A. A reasonable approach when requirements are well defined.

Q169: The linear sequential model of software development is also known as the

Answer option

  • A. Classical life cycle model
  • B. Fountain model
  • C. Spiral model
  • D. Waterfall model
Answer

Answer D. Waterfall model

Q170: The incremental model of software development is

Answer option

  • A. A reasonable approach when requirements are well defined
  • B. A good approach when a working core product is required quickly
  • C. The best approach to use for projects with large development teams
  • D. A revolutionary model that is not used for commercial products
Answer

Answer B. A good approach when a working core product is required quickly.

Q171: The rapid application development model is

Answer option

  • A. Another name for component-based development
  • B. A useful approach when a customer cannot define requirements clearly
  • C. A high-speed adaptation of the linear sequential model
  • D. All of the above
Answer

Answer C. A high-speed adaptation of the linear sequential model.

Q172: Evolutionary software Process models

Answer option

  • A. Are iterative in nature
  • B. Can easily accommodate product requirements changes
  • C. Do not generally produce throwaway systems
  • D. All of the above
Answer

Answer D. All of the above

Q173: The prototyping model of software development is

Answer option

  • A. A reasonable approach when requirements are well defined
  • B. A useful approach when a customer cannot define requirements clearly
  • C. The best approach to use for projects with large development teams
  • D. A risky model that rarely produces a meaningful product
Answer

Answer B. A useful approach when a customer cannot define requirements clearly.

Q174: The spiral model of software development

Answer option

  • A. Ends with the delivery of the software product
  • B. Is more chaotic than the incremental model
  • C. Includes project risks evaluation during each iteration
  • D. All of the above
Answer

Answer C. Includes project risks evaluation during each iteration

Q175: The concurrent development model is

Answer option

  • A. Another name for the rapid application development model
  • B. Often used for the development of client/server applications
  • C. Only used for development of parallel or distributed systems
  • D. Used whenever a large number of change requests are anticipated
Answer

Answer D. Used whenever a large number of change requests are anticipated.

Q176: The component-based development model is

Answer option

  • A. Only appropriate for computer hardware design
  • B. Not able to support the development of reusable components
  • C. Works best when object technologies are available for support
  • D. Not cost effective by known quantifiable software metrics
Answer

Answer C. Works best when object technologies are available for support.

Q177: The formal methods model of software development makes use of mathematical methods to

Answer option

  • A. Develop defect free computer-based systems
  • B. Define the specification for computer-based systems
  • C. Verify the correctness of computer-based systems
  • D. All of the above
Answer

Answer C. Verify the correctness of computer-based systems

Q178: The analysis and design of application systems are the responsibility of a___

Answer option

  • A. Computer Operator
  • B. Programmer
  • C. System Analyst
  • D. Data entry operator
Answer

Answer C. System Analyst

Q179: The DBA is

Answer option

  • A. a person
  • B. a computer device
  • C. a communication technique
  • D. All of the above
Answer

Answer A. a person

Q180: A constraint that does not, affect the feasible solution region is known as

Answer option

  • A. redundant constraint
  • B. unbounded solution
  • C. slack variable
  • D. surplus variable
Answer

Answer C. slack variable

Q181: Computer support to the manager has been least in

Answer option

  • A. alternative identification
  • B. alternative selection
  • C. problem identification
  • D. alternative evaluation
Answer

Answer A. alternative identification

Q182: A___is a brief message to an operator that describes what data are to be entered.

Answer option

  • A. prompt
  • B. passwords
  • C. MIS
  • D. Tactical
Answer

Answer A. prompt

Q183: Which of the following is not true about expert systems?

Answer option

  • A. Expert systems are collections of human knowledge
  • B. Export systems are expensive to design
  • C. export systems are usually designed to run on small general-purpose computers
  • D. Maintenance support may be difficult to obtain for an expert system
Answer

Answer D. Maintenance support may be difficult to obtain for an expert system.

Q184: General ledger is also referred to as:

Answer option

  • A. extra ledger
  • B. main ledger
  • C. nominal ledger
  • D. All of the above
Answer

Answer C. nominal ledger

Q185: In the preliminary investigation phase of the SDLC, which of the following tasks would not be included?

Answer option

  • A. briefly defining the problem
  • B. suggesting alternative solutions
  • C. gathering the data
  • D. preparing a short report
Answer

Answer B. suggesting alternative solutions