Cost Management MCQ set 2

41. What is the ideal transfer price?
A. Market price
B. Total cost
C. Total cost less internal savings
D. Opportunity cost

Answer

D. Opportunity cost

42. In what circumstances might a company be prepared to price a special contract at less than itsrelevant cost?
A. When sales of other products will not increase
B. When the company is operating at almost full capacity
C. In the expectation that additional profitable orders will be placed by the same customer
D. When there are signs of improved market conditions

Answer

C. In the expectation that additional profitable orders will be placed by the same customer

43. The standard cost of a product is:
A. The average unit cost of products produced during a particular period
B. The unit cost of products incurred at the start of a particular period
C. The average unit cost of products produced in the previous period
D. The planned unit cost of products produced during a particular period

Answer

D. The planned unit cost of products produced during a particular period

44. What term is used to describe the level of efficiency achieved that appropriately trained, motivated and resourced employees can achieve in the long-run?
A. Standard performance
B. Standard hours
C. Standard ex ante
D. Standard ex post

Answer

B. Standard hours

45. A standard that represents the most likely scenario can be referred to as the:
A. Average standard
B. Attainable standard
C. Basic standard
D. Ideal standard

Answer

B. Attainable standard

46. When calculating cost variances under a standard costing system we must:
A. Compare standard costs with actual costs at the standard level of activity
B. Compare actual costs with those that were budgeted
C. Compare actual costs with standard costs at the actual level of output
D. Compare actual outputs against budgeted outputs

Answer

D. Compare actual outputs against budgeted outputs

47. When carrying out variance analysis ideally, we should:
A. Look at controllable adverse and favourable variances that are over a predetermined amount
B. Look at adverse variances that are over a predetermined amount
C. Look at all variances
D. Look at all adverse and favourable variances that are over a predetermined amount

Answer

A. Look at controllable adverse and favourable variances that are over a predetermined amount

48. The efficiency ratio can be defined as:
A. Actual hours worked / budgeted labour hours
B. Standard hours produced/ actual labour hours worked
C. Standard hours produced / budgeted labour hours
D. Actual hours worked / actual production based on standard hours

Answer

A. Actual hours worked / budgeted labour hours

49. The labour rate variance can be calculated by the following equation:
A. (Standard hours – actual hours) x actual wage rate
B. (Standard wage rate – actual wage rate) x standard hours worked
C. (Standard wage rate – actual wage rate) x actual hours worked
D. Budgeted labour costs – actual labour costs

Answer

A. (Standard hours – actual hours) x actual wage rate

50. In August actual material used amounted to 5,650 kg, budgeted output was 1,000 units and standard material usage was 5 kg per unit. Actual output was 1,075 units. If the standard material cost of each product is 25 the material efficiency variance will be:
A. 3,250 favourable
B. 1,375 favourable
C. 3,250 adverse
D. 1,375 adverse

Answer

C. 3,250 adverse

51. During July actual labour costs amounted to 19,800, the standard rate of pay was 4.50 per hourand the labour rate variance amounted to 225 adverse. The actual hours worked were:
A. 4,400
B. 1,012
C. 4,350
D. 3,450

Answer

A. 4,400

52. An adverse material usage variance together with a favourable materials price variance could suggest that:
A. We are paying the same for our materials but we are using more than expected
B. We are paying higher prices for our materials than expected
C. We are paying less for our materials than expected but we are using more materials
D. We are using less material than expected but in total we are paying more than we should

Answer

A. We are paying the same for our materials but we are using more than expected

53. An adverse labour efficiency variance together with a favourable labour rate variance may mean that:
A. The business is paying a higher hourly rate than the standard
B. Less labour hours are needed to make the same amount of output
C. Less skilled staff are being used in production
D. More products are being made per hour

Answer

C. Less skilled staff are being used in production

54. The formula for calculating the variable overhead total variance is:
A. (Standard hours less actual hours) x variable overhead absorption rate
B. Actual variable overhead less (actual hours x actual hours worked x variable overhead absorption rate)
C. Actual variable overhead expenditure less budgeted variable overhead expenditure
D. Actual variable overhead less (standard hours x actual production x variable overhead absorption rate)

Answer

B. Actual variable overhead less (actual hours x actual hours worked x variable overhead absorption rate)

55. The formula for calculating the fixed overhead volume variance is:
A. Budgeted fixed expenditure less (actual hours x actual production x fixed overhead absorption rate)
B. Budgeted fixed expenditure less (actual hours x fixed overhead absorption rate)
C. Actual fixed overhead less (standard hours x actual production x fixed overhead absorption rate)
D. Budgeted fixed expenditure less (standard hours x actual production x fixed overhead expenditure variance)

Answer

D. Budgeted fixed expenditure less (standard hours x actual production x fixed overhead expenditure variance)

56. ___ are the factor which have direct cause and effect relationship with cost
A. Cost object
B. Cost pool
C. Cost driver
D. Cost centre

Answer

C. Cost driver

57. ___ is also known as ‘Transaction Costing’.
A. Target costing
B. Kaizen costing
C. Throughput costing
D. Activity based costing

Answer

D. Activity based costing

58. ___ is maximum permissible cost in a competitive business environment.
A. Activity cost
B. Target cost
C. Kaizen cost
D. None of these

Answer

B. Target cost

59. Promoters of Activity based Costing was /were ___
A. Kaplan and Cooper
B. Galloway
C. Goldratt
D. Ouchy

Answer

A. Kaplan and Cooper

60. In innovative cost management terminologies ‘BPR’ stands for?
A. Business Process Reconstruction
B. Business Production Reschedule
C. Business Process Re-engineering
D. None of these

Answer

C. Business Process Re-engineering

61. A cost centre is:
A. The part of the business where all costs are paid to suppliers
B. A production department where all production costs are aggregated
C. An area for which costs are accumulated
D. An area of the business accountable for both costs and revenues

Answer

C. An area for which costs are accumulated

62. An investment centre is a responsibility centre where the manager has control of:
A. Costs
B. Costs, profits and product quality
C. Costs, profits and assets
D. Costs and profits

Answer

C. Costs, profits and assets

63. Responsibility accounting aims to:
A. Ensure that costs become the responsibility of a specific manager
B. Ensure that a manager is punished if things go wrong
C. Reduce the costs that a department incurs
D. Allocate costs to all areas of a business

Answer

A. Ensure that costs become the responsibility of a specific manager

64. Prime cost can be defined as:
A. The total costs of manufacturing a product
B. The total direct costs of manufacturing a product
C. The total costs of operating the production department where the product is made
D. The cost of the first stage of the manufacture of a product

Answer

B. The total direct costs of manufacturing a product

65. Which of the following best describes a fixed cost?
A. Has a direct relationship with output
B. Increases proportionately with output
C. Represents a fixed proportion of total costs
D. Remains constant irrespective of the level of activity

Answer

D. Remains constant irrespective of the level of activity

66. Direct labour costs will include:
A. Direct labour costs plus any bonuses and overtime premiums
B. Direct labour costs plus any bonuses
C. Total direct labour hours at the normal hourly rate of pay
D. All labour costs attributable to a product

Answer

C. Total direct labour hours at the normal hourly rate of pay

67. The company which applied first ‘Just in Time’ in its manufacturing is ___
A. GE Electricals
B. Motorola
C. Toyota
D. Suzuki

Answer

C. Toyota

68. ___ is developed on the concept ‘inventory is evil’.
A. Quality circle
B. JIT
C. Kaizen
D. All of these

Answer

B. JIT

69. JIT was first developed by:
A. Taiichi Ohno
B. Ouchy
C. Kaplan
D. None of these

Answer

A. Taiichi Ohno

70. “Kanban’ system is similar to ___ philosophy
A. Kaizen
B. Cost driver
C. Just in Time
D. None of these

Answer

C. Just in Time

71. Which of the following is / are the method of establishing ‘target cost’?
A. Addition method
B. Subtraction method
C. Integration method
D. All of these

Answer

D. All of these

72. Accumulated cost of an activity called ___ in Activity based costing.
A. Cost driver
B. Cost object
C. Cost centre
D. Cost Pool

Answer

D. Cost Pool

73. ___ is regarded as ‘Price-led costing’.
A. Activity based costing
B. Target costing
C. Kaizen costing
D. Back flush costing

Answer

B. Target costing

74. Life Cycle Costing is advocated by ___
A. R. Kaplan
B. R. Cooper
D. G. Woodward d. S. Goldratt

Answer

C.

75. Upstream cost, Down stream cost etc., are the concepts in ___
A. Target costing
B. Kaizen costing
C. Life cycle costing
D. Activity based costing

Answer

C. Life cycle costing

76. When output in relation to the input is expressed mathematically it is called as ___
A. Outcome index
B. Efficiency index
C. Productivity index
D. All the above.

Answer

C. Productivity index

77. If Profit divided by the capital employed, it reveals ___
A. Labour productivity
B. Machine productivity
C. Material productivity
D. None of these

Answer

D. None of these

78. The type of spoilage that should not affect the cost of inventories is
A. Abnormal spoilage
B. Seasonal spoilage
C. Normal spoilage
D. Indirect spoilage

Answer

A. Abnormal spoilage

79. Materials may not be put into process
A. At the beginning of an operation
B. Continuously
C. At the end of the operation
D. In the shipping department.

Answer

D. In the shipping department.

80. Process cost method is especially suitable for
A. Custom production
B. FIFO
C. Standard costs
D. LIFO

Answer

C. Standard costs

ed010d383e1f191bdb025d5985cc03fc?s=120&d=mm&r=g

DistPub Team

Distance Publisher (DistPub.com) provide project writing help from year 2007 and provide writing and editing help to hundreds student every year.