Business Math Online Objective Set 5

Online Assignment for Business Math Set 5

QN1. The matrix is an arrangement of numbers in___
a. m rows & n columns
b. n rows & m columns
c. both a & b
d. none of the above.

Answer

Answer: A

QN2. The value of the determinant
word image 1122 is _____
a.100.
b.364.
c.14.
d.340.

Answer

Answer: B

QN3. Zero matrix is also called____.
a. Diagonal matrix
b.Scalar matrix
c.Unit matrix
d.Null matrix

Answer

Answer: D

QN4. The rank of the given matrix
word image 1123 is
a.1
b.2
c.3
d.0

Answer

Answer: B

QN5. The order of
word image 1124 is
a.3×3
b.2×3
c.3×2
d.4×4

Answer

Answer: B

QN6. If A is
word image 1125 is
a.0
b.l
c.2
d.3

Answer

Answer: C

QN7. The given matrix is
word image 1126
a. a scalar matrix.
b. a unit matrix.
c. a square matrix
d. a rectangular matrix.

Answer

Answer: D

QN8.1f A=
word image 1127
word image 1128

Answer

Answer: C

QN9. If A is a singular matrix |A| is____
a.1
b.0
c. any positive value.
d. any negative value

Answer

Answer: B

QN10. If
word image 1129
a. square matrices.
b. null matrices.
c. row matrices.
d. zero matrices.

Answer

Answer: A

QN11. If A, B are two matrices and K is a scalar then
word image 1130

Answer

Answer: B

QN12. If A,B and C are matrices the associative property is___
word image 1131

Answer

Answer: D

QN13. Zero matrix is otherwise known as____
a. null matrix.
b. square matrix.
c.unit matrix.
d.triangular matrix.

Answer

Answer: A

QN14. If Aand B are matrices of same order then
word image 1132

Answer

Answer: A

QN15. If A,B and C are matrices of the same order then
word image 1133

Answer

Answer: A

QN16. The determinant value of the following matrix
word image 1134
a.47
b.40
c.57
d.-57

Answer

Answer: A

QN17. When the number of rows and the number of columns of a matrix are equal, the matrix is___
a.square matrix
b.row matrix
c.column matrix
d.none of these.

Answer

Answer: A

QN18. If all the elements of a matrix are zeros, then the matrix is a___
a.unit matrix
b.square matrix
c.zero matrix
d.none of these.

Answer

Answer: C

QN19. A diagonal matrix in which all the diagonal elements are equal is a ___
a.scalar matrix
b.column matrix
c.unit matrix
d.None of these.

Answer

Answer: A

QN20. If any two rows and columns of a determinant are identical, the value of the determinant is___
a.1
b.0
c.-1
d.Unaltered

Answer

Answer: B

QN21. .If there is only one column in a matrix, it is called___
a.Row matrix
b.column matrix
c.square matrix
d.rectangular matrix.

Answer

Answer: B

QN22.When all the elements of a matrix are zeros, the matrix is called____
a.unit matrix
b.square matrix
c.null matrix
d.Row matrix.

Answer

Answer: C

QN23.When the number of rows is not equal to the number of columns then the matrix is said to be____
a.unit matrix
b. Rectangular matrix
c .null matrix
d.row matrix.

Answer

Answer: B

QN24.The Value of determinant of
word image 1135
a. -27.
b. 27.
c. 24.
d. -24.

Answer

Answer: A

QN25. .If the number of rows of a matrix is greater than the number of columns then the matrix is called as___
a. a row matrix
b.a column matrix
c.a rectangular matrix
d.a square matrix.

Answer

Answer: C

QN26. Inverse of a matrix exists if and only if___
a.determinant value exists
b.determinant value is zero
c.determinant value is one
d.determinant value is negative

Answer

Answer: A

QN27.A square matrix A is an orthogonal matrix x, if___
word image 1136

Answer

Answer: B

QN28. (3 8 9 -2 ) is a row matrix of order___
a.4×4
b.1×4
c.1×1
d.4×1.

Answer

Answer: B

QN29.If
word image 1137
word image 1138

Answer

Answer: A

QN30.Cramer’s Rule is also known as___
a. Inverse Matrix Method
b. Matrix Method
c. Determinant Method
d. Inverse Method

Answer

Answer: C

QN31. The___is the order of the largest square submatrix.
a. Rank of a matrix
b. Size of a matrix
c. Both a & b
d. None of the above.

Answer

Answer: A

QN32. O.R. Stands for___
a. Operations research
b. Open Report
c. Own Record
d. On Road

Answer

Answer: A

QN33. If a matrix has 4 rows and 3 columns, then the size will be denoted by
a.3×4
b.3×3
c.4×3
d.4×4

Answer

Answer: C

QN34. I stands for
a. Simple Interest
b. Compound Interest
c. Rate of interest
d. No.of.years.

Answer

Answer: A

QN35.C.I. stands for .
a. Compound Interest
b. Simple Interest
c. Rate Of Interest
d. No.of.years.

Answer

Answer: A

QN36. Principal (or) Present Value is denoted by
a. A
b. n
c. P
d. None of the above.

Answer

Answer: C

QN37. The Lender’s are also known as____
a. Creditor’s
b. Debtor’s
c. Buyer’s
d. None of the above.

Answer

Answer: A

QN38.The borrowers are also known as___
a. Debtor’s
b. Creditor’s
c. Both a & b
d. None of the above.

Answer

Answer: A

QN39. Compound Interest is always___the Simple Interest.
a. Lesser than
b. Equal to
c. Greater than
d. None of the above.

Answer

Answer: C

QN40.Simple interest will be the income for___
a.lender.
b.borrower.
c.both .
d.neither lender nor borrower.

Answer

Answer: A

QN41.The simple interest on Rs 5,000 at 10% for 3 years is
a.500.
b.1000.
c.1500.
d.2000.

Answer

Answer: C

QN42.The formula for the face value A is given by___
word image 1139

Answer

Answer: B

QN43.Under annuity due, payment is due at the
a.beginning of the time
b.end of the time.
c.at the middle of the time.
d.each .

Answer

Answer: A

QN44.The compound interest for Rs 20000 for 3 years at 10 % is
a.2500.
b.2200.
c.6000.
d.2500.

Answer

Answer: C

QN45.The simple interest for Rs 10000 for 2 years at 10% is
a.200.
b.3000.
c.4000.
d.2000.

Answer

Answer: D

QN46. 51-46+3(5) =
a. 40
b. 20
c. 41
d.52

Answer

Answer: B

QN47. 3x- 4+7 = 0, then x =?
a. -1
b. +1.
c. 0.
d. 2.

Answer

Answer: A

QN48.Under compound interest the formula for A is given by
a.A=P(1+ni).
b.A=P(1+i).
c.A=Pnr/100. d.A=P(1+i)n.

Answer

Answer: D

QN49.Banker’s discount is given by the formula___.
a.Anr/100.
b.Pnr/100.
c.Anr.
d.Pnr.

Answer

Answer: A

QN50.Face value of a bill of exchange is given by the formula___
word image 1140

Answer

Answer: B

QN51.When the payments are to be made at the end of each interval the annuity is called___
a.immediate annuity.
b.annuity due.
c.both( a) and( b).
d.present annuity.

Answer

Answer: A

QN52. In calculation of interest ‘n’ stands for
a. Rate of interest
b. Amount
c. Principal
d. No.of.years

Answer

Answer: D

QN53.The formula for finding the compound interest is___
a.A=P(1+ni).
b.A=P(1+i).
c.A=Pnr/100.
d.A=P(1+i)n.

Answer

Answer: D

QN54.Under simple interest, the interest for n years is
a.A=P(1+ni).
b.A=P(1+i).
c.A=Pnr/100.
d.A=P(1+i)n.

Answer

Answer: C

QN55.Under simple interest, amount or value at the end is
a.A=P+I.
b.A=P(1+i).
c.A=Pnr/100.
d.A=P(1+i)n.

Answer

Answer: A

QN56.Under simple interest, the rate of interest is given by
a. R = 100r-(100-nr).
b. r = 100 I/Pn.
c. Anr/100.
d. A=P(1+i)n.

Answer

Answer: B

QN57.The present value under annuity due is____
word image 1141

Answer

Answer: A

QN58.The Amount due under immediate annuity is___
word image 1142

Answer

Answer: D

QN59.Formula for Bankers gain is___
word image 1143

Answer

Answer: B

QN60.In Graphical solution the feasible region is____
a.where all the constraints are satisfied simultaneously.
b.any one constraint is satisfied
c.only the first constraint is satisfied
d.any one of the above condition.

Answer

Answer: A

QN61.An LPP has___.
a.one optimal solution
b.two optimal solutions
c.Three optimal solutions
d.none of these.

Answer

Answer: D

QN62.An LPP deals with problems involving only___
a.single objective
b.multiple objective
c.two objective
d.none of these.

Answer

Answer: A

QN63.Which of the following is not associated with any LPP?
a.Feasible Solution
b.Optimum Solution
c.Basic solution
d.Quadratic equation.

Answer

Answer: D

QN64.Which of the following is not true about feasibility?
a.It cannot be determined in a graphical solution of an LPP.
b.It is independent of the objective function.
c.It implies that there must be a convex region satisfying all the constraints.
d.Extreme points of the convex region give the optimum solution.

Answer

Answer: A

QN65.In Graphical solution the feasible solution is any solution to a LPP which satisfies____
a.only objective function.
b.non-negativity restriction.
c.only constraint.
d.all the three.

Answer

Answer: B

QN66.In Graphical solution the redundant constraint is___
a.which forms the boundary of feasible region.
b.which do not optimizes the objective function.
c.which does not form boundary of feasible region.
d.which optimizes the objective function.

Answer

Answer: C

QN67.Optimal solution in an LPP is___
a.which maximizes or minimizes the objective function.
b.which maximizes the objective function.
c.which minimizes the objective function.
d.which satisfies the non negativity restrictions.

Answer

Answer: A

QN68.Unbounded solution in an LPP is___
a.where the objective function can be decreased indefinitely.
b.which maximizes the objective function.
c.where the objective function can be increased or decreased indefinitely
d.where the objective function can be increased indefinitely.

Answer

Answer: C

QN69.The two forms of LPP are ___
a.standard form and canonical form
b.standard form and general form
c.matrix form and canonical form
d.matrix form and standard form.

Answer

Answer: A

QN70.In the canonical form of LPP if the objective function is of maximization, then all the constraints other than non-negativity conditions are ___
a.greater than type.
b.lesser than type.
c.greater than or equal to type.
d.lesser than or equal to type.

Answer

Answer: D

QN71.In the canonical form of LPP if the objective function is of minimization then all the constraints other than non-negativity conditions are___
a. greater than type.
b. lesser than type.
c. greater than or equal to type.
d. lesser than or equal to type.

Answer

Answer: C

QN72.In an LPP the solution for the problems involving more than 2 variables can be solved using___
a. graphical method.
b. simplex method.
c. hungarian method.
d. all the above

Answer

Answer: B

QN73.In the standard form of LPP if the objective functions is of minimization then all the constraints___
a. equations .
b. inequalities.
c. greater than or equal to type.
d. lesser than or equal to type.

Answer

Answer: A

QN74.In the standard form of LPP if the objective function is of minimization then the right hand side of the constraints should be ____
a. positive.
b. negative.
c. non-negative.
d. zero.

Answer

Answer: C

QN75.The non-negative variable which is added to LHS of the constraint to convert the inequality ≤ into equation is called___
a. random variable.
b. decision variable.
c. surplus variable.
d. slack variable.

Answer

Answer: D

QN76.The non-negative variable which is added to LHS of the constraint to convert the inequality ≥ into equation is called___
a.random variable.
b.decision variable
c.surplus variable
d.slack variable.

Answer

Answer: C

QN77.The test of optimality in simplex method is
word image 1144

Answer

Answer: A

QN78.The Key column in simplex method is selected when the column of Zj-Cj is
a. most negative.
b. largest negative.
c. positive.
d. zero.

Answer

Answer: A

QN79.The Key row is selected when the column of Zj-Cj is finding the ratio which is
a. maximum.
b. minimum.
c. largest positive.
d. most negative.

Answer

Answer: B

QN80.In simplex method the LPP has unbounded solution if the variable in the key column is____
a. maximum.
b. minimum.
c. positive.
d. negative.

Answer

Answer: D

QN81.In graphical method the LPP has unbounded solution if the solution space has
a. no upper boundary.
b. no lower boundary.
c. no boundary in the first quadrant.
d. none of the above.

Answer

Answer: A

QN82.In a linear programming minimization model the objective function is to be___
a.minimized
b.maximized.
c.minimized or maximized.
d.standardized.

Answer

Answer: A

QN83.Which of the following is associated with any L.P.P?
a.feasible solution
b.optimum solution
c.basic solution
d.all the above.

Answer

Answer: D

QN84.Linear programming is___
a.a constraint optimization model
b.a constraint decision making model.
c.a mathematical programming model.
d.all the above.

Answer

Answer: D

QN85.Which of the following is not true about feasibility?
a.it cannot be determined in a graphical solution of an L.P.P.
b.it is independent of the objective function.
c.it implies that there must be a convex region satisfying all the constraints.
d.extreme points of the convex region gives the optimum solution.

Answer

Answer: A

QN86.Graphical method can be used only when the decision variables is___.
a.more than 3
b.more than 1
c.two
d.one

Answer

Answer: C

QN87.The region on the graph sheet with satisfies the constraints including the non negativity restrictions is called the____space
a.solution.
b.interval
c.concave.
d.convex.

Answer

Answer: A

QN88.The ___ is the method available for solving an L.P.P.
a.graphical method.
b.least cost method.
c.MODI method
d.hungarian method.

Answer

Answer: A

QN89. The graphical method is applicable to solve an L.P.P when there is___
a.Only one variable
b.Two variables
c.More than two variables
d.None of the above.

Answer

Answer: B

QN90.The objective of network analysis is to___
a.Minimize total project duration.
b.Minimize total project cost.
c.Minimize product delays,interruption and conflicts
d.All the above.

Answer

Answer: A

QN91. Network models have advantage in terms of project___
a.Planning
b.Scheduling
c.Controlling
d.All the above.

Answer

Answer: D

QN92.The slack for an activity is equal to___
a.LF-LS.
b.EF-ES.
c.LS-ES.
d.None of the above.

Answer

Answer: C

QN93.The another term commonly used for activity slack time is___
a.Total float
b.Independent float
c.Free float
d.All the above.

Answer

Answer: D

QN94.Generally the PERT technique deals with the project of
a.Repetatative nature
b.Non-repetative nature
c.Determinstic nature
d.None of the above.

Answer

Answer: B

QN95.In PERT the span of time between the optimistic and pessismistic time estimates of an activity is___
word image 1145

Answer

Answer: B

QN96.If an activity has zero slack,it implies that___
a.It lies on the critical path.
b.It is a dummy acitivity.
c.The project is progressing well.
d.None of the above.

Answer

Answer: A

QN97.A dummy activity is used in the network diagram when___
a.Two parallel activities have the same tail and head events.
b.The chain of acitivities may have a common event yet he independent by themselves. c.Both a & b
d.None of the above.

Answer

Answer: C

QN98.While drawing the network diagram for each activity project we should look___
a.What acitivities preceede this acitivity .
b. What acitivities follow this acitivity.
c.What activity can concurrently take place with this activity.
d.All the above.

Answer

Answer: D

QN99.In the PERT network each activity time assumes
a Beta distribution because
a.It is a unimodal distribution that provides information regarding the uncertainity of time estimates of activities.
b.It has got finite non-negative error.
c.It need not be symmetrical about model value
d.All the above

Answer

Answer: D

QN100.The critical path satisfy the condition that
word image 1146

Answer

Answer: A

QN101.Float or slack analysis is useful for___
a.Projects behind the schedule only
b.Projects ahead of the schedule only
c.Both a & b
d.None of the above.

Answer

Answer: A

QN102.The acitivity that can be delayed without affecting the execution of the immediate succeeding activity is determined by____
a.Total float
b.Independent float
c.Free float
d.None of the above.

Answer

Answer: B

QN103.In time cost trade off function analysis___
a.Cost decreases linearily as time increases
b.Cost at normal time is zero
c.Cost increses linearily as time increases
d.None of the above.

Answer

Answer: A

QN104.Activity -on-arrow (AOA) diagram is prefeered over Activity -on-node (AON) diagram because___
a.AOA diagrams are simple to construct.
b.AOA diagrams give a better sense of the flow of time throughout a project.
c.AOA diagrams do not involve dummy activites
d.ALL the above.

Answer

Answer: B

QN105.Resource leveling is the process of ___the utilization of resources in a project.
a. Emerging
b.Smoothing out.
c. Minimize
d. Maximize

Answer

Answer: B

QN106.Crashing is the process of reducing the total time that it takes to complete a project by expanding___
a.Additional funds.
b. No.of.days
c. Both a & b
d. None of the above

Answer

Answer: A

QN107. ____is the time consuming job (or) task that is a key subpart of the total project
a.Activity
b.Event
c.Node
d.All the above.

Answer

Answer: A

QN108.Earliest finish time that an activity can be finished without___of precedence requirements.
a. Planning
bViolation
c. Both a&b
d. None of the above

Answer

Answer: B

QN109. ____is the point in time that marks the beginning or ending of an activity.
a.Event
b.Node
c.Activity
d.Dummy activity

Answer

Answer: A

QN110. If an activity has a zero slack, it implies that
a. It lies on the critical path
b. It is a dummy activity
c. Both a & b
d. None of the above

Answer

Answer: A

QN111.Network is the graphical display of a project that contains both___and___
a.Activities and events
b.Activities and dummy activities
c. Both (a) &(b)
d.Neither (a) nor (b).

Answer

Answer: A

QN112.A small circle or rectangle that is known as___serves as a junction point in the project network
a.Event
b.Node
c.Slack
d.Variables

Answer

Answer: B

QN113.Latest finish time that an activity can be finished without___the entire project.
a.Delaying.
b. Planning
c. Both a&b
d. None of the above

Answer

Answer: A

QN114.The amount of time that is expected to complete the activity is called___
a.Latest time
b.Earliest time
c.Most likely time.
d.Both a & b .

Answer

Answer: C

QN115.PERT is a tool for___and control time.
a. Delaying. b.Planning.
c. Both a&b
d. None of the above

Answer

Answer: B

QN116.The CPM is used for completing the project that involves___of repetitive nature.
a.Activities
b.Node
c.Event.
d.Dummy activity

Answer

Answer: A

QN117.Project___phase allocates resources to work packages.
a. Planning
b.Scheduling
c.Controlling
d.Both b&c.

Answer

Answer: A

QN118. ___phase identify manpower that will be responsible for each task.
a. Planning
b.Scheduling
c.Controlling
d.All the above.

Answer

Answer: B

QN119.A ____is an endeavour to create a unique product service.
a.Project
b.Network
c.Activity
d.Node.

Answer

Answer: A

QN120. Transportation problem is a special class of___
a.LPP
b.assignment problem
c.none of the two
d.both 1 and 2.

Answer

Answer: A

QN121.The Objective function of Transportation problem is to___
a.maximize the total cost.
b.minimize or maximize the total cost.
c.minimize the total cost.
d.total cost should be zero.

Answer

Answer: C

QN122. In Transportation problem the preferred method of obtaining either optimal or very close to the optimal solution is___
a..north west corner rule
b.least cost method
c.vogel’s approximation method
d.simplex method.

Answer

Answer: C

QN123.In Transportation problem the improved solution of the initial basic feasible solution is called___
a.basic solution
b.optimal solution
c.degenerate solution
d.non-degenerate solution.

Answer

Answer: B

QN124.In Transportation problem optimal solution can be verified by using___
a.north west corner rule
b.least cost method
c.MODI method
d.matrix method.

Answer

Answer: C

QN125.The cells in the Transportation problem can be classified as___
a.assigned cells and empty cells
b.allocated cells and un allocated cells
c.occupied and unoccupied cells
d.assigned and unoccupied cells

Answer

Answer: C

QN126.In North West corner rule the allocation is done in___
a.upper right corner
b.middle cell in the transportation table
c.cell with the lowest cost
d.Upper left corner.

Answer

Answer: D

QN127.In Least cost method the allocation is done by selecting____
a.upper left corner.
b.upper right corner.
c.middle cell in the transportation table.
d.cell with the lowest cost.

Answer

Answer: D

QN128. Transportation problem is said to be balanced if a.total supply is not equal to total demand. b.total supply is greater than total demand. c.total supply is lesser than total demand. d.total supply is equal to total demand.

Answer

Answer: D

QN129.Transportation problem is said to be unbalanced if___
a.total supply is not equal to total demand
b.Tot al supply is greater than total demand
c.total supply is lesser than total demand
d. All the above

Answer

Answer: D

QN130.The basic feasible solution to a transportation problem is said to be optimal if it___
a.maximizes or minimizes the transportation cost
b.maximizes the transportation cost
c.minimizes the transportation cost
d.has degenerate solution.

Answer

Answer: C

QN131.The necessary and sufficient condition for the existence of a feasible solution to a transportation problem is a solution that satisfies all the conditions of___
a.supply
b.demand.
c.supply and demand
d.either supply or demand

Answer

Answer: C

QN132.Purpose of MODI method is to get
a.degenerate solution
b.non-degenerate solution
c.optimal.
d.basic feasible solution.

Answer

Answer: C

QN133.In transportation problem the solution is said to non-degenerate solution if occupied cells is___.
a. greater than m+n-1.
b. lesser than m+n-1.
c. greater than or equal to m+n-1.
d. lesser than or equal to m+n-1.

Answer

Answer: C

QN134.In transportation problem the solution is said to degenerate solution if occupied cells is
a.greater than m+n-1.
b.lesser than m+n-1.
c.greater than or equal to m+n-1.
d.lesser than or equal to m+n-1.

Answer

Answer: B

QN135.In transportation problem if total supply > total demand we add___
a.dummy row with cost 0
b.dummy column with cost 0
c.dummy row with cost 1
d.dummy column with cost 1.

Answer

Answer: B

QN136.In transportation problem if total supply < total demand we add___
a.dummy row with cost 0
b.dummy column with cost 0
c.dummy row with cost 1
d.dummy column with cost 1

Answer

Answer: A

QN137.In North West corner rule if the demand in the column is satisfied one must move to the____
a.left cell in the next column
b.right cell in the next row
c.right cell in the next column
d.left cell in the next row

Answer

Answer: C

QN138.In North West corner rule if the supply in the row is satisfied one must move
a.down in the next row
b.up in the next row
c.right cell in the next column
d.left cell in the next row.

Answer

Answer: A

QN139.The objective of the transportation problem which is to be maximized is to
a.maximize the total profit
b.minimize the total loss
c.neither maximize nor minimize
d.optimal cost.

Answer

Answer: A

QN140.In Maximization case of transportation problem we convert into minimization by subtracting all the elements from the___
a.zero
b.one.
c.highest element
d.lowest element.

Answer

Answer: C

QN141.The application of assignment problems is to obtain___
a.only minimum cost
b.only maximum profit
c.minimum cost or maximum profit
d.assign the jobs.

Answer

Answer: D

QN142.The assignment problem is said to be unbalanced if___
a.number of rows is greater than number of columns
b.number of rows is lesser than number of columns
c.number of rows is equal to number of columns
d.both 1 and 2.

Answer

Answer: D

QN143.The assignment problem is said to be balanced if___
a.number of rows is greater than number of columns
b.number of rows is lesser than number of columns
c.number of rows is equal to number of columns
d.if the entry of row is zero.

Answer

Answer: C

QN144.The assignment problem is said to be balanced if it is___
a.square matrix
b.rectangular matrix
c.unit matrix
d.triangular matrix.

Answer

Answer: A

QN145.In assignment problem if number of rows is greater than column then___ a.dummy column is added
b.dummy row added
c.row with cost 1 is added
d.column with cost 1 is added.

Answer

Answer: A

QN146.In assignment problem if number of column is greater than row then___
a.dummy column is added
b. dummy row added .
c. row with cost 1 is added.
d. column with cost 1 is added.

Answer

Answer: B

QN147.The transportation technique or simplex method cannot be used to solve the assignment problem because of___
a.degeneracy
b.non-degeneracy
c.square matrix
d.any one of the above.

Answer

Answer: A

QN148.The objective of Transportation problem is to allocate___
a.number of origins to equal number of destinations at minimum cost
b.number of origins to equal number of destination at maximum cost
c.only to maximize cost
d.only to maximize the profit.

Answer

Answer: A

QN149. In transportation problem ‘NWC’ stands for___
a. North West Corner
b. Net Working Capital
c. Naval Weapons Center
d. Nuclear Weapons Convention

Answer

Answer: A

QN150. Vogel’s approximation method is also known as___
a. Penalty method
b. North west method.
c. Least cost method
d. None of the above.

Answer

Answer: A

ed010d383e1f191bdb025d5985cc03fc?s=120&d=mm&r=g

DistPub Team

Distance Publisher (DistPub.com) provide project writing help from year 2007 and provide writing and editing help to hundreds student every year.