Q51472 Michigan manufacturing produces a product that has a 6-month demand cycle, as shown in Table 1. Each unit requires 10 worker-hours to produce, at a labour cost of Rs. 6 per hour regular rate (or Rs. 9 per hour overtime). The total cost per unit is estimated at Rs. 200, but units can be subcontracted at a cost of Rs. 208 per unit. There are currently 20 workers employed in the subject department, and hiring and training costs for additional workers are Rs. 300 per person, whereas layoff costs are Rs. 400 per person. Company policy is to retain a safety stock equal to 20 per cent of the monthly forecast, and each month’s safety stock becomes the beginning inventory for the next month. There are currently 50 units in stock carried at a cost of Rs. 2 per unit-month. Unit shortage, or stockouts, has been assigned a cost of Rs. 20 per unit month.

  January February March April May June
Forecast demand 300 500 400 100 200 300
Workdays 22 19 21 21 22 20
Work hr at 8 per day 176 152 168 168 176 160
Table No. 1

Three aggregate plans are proposed.

Plan 1: Vary work force size to accommodate demand.

Plan 2: Maintain constant work force of 20, and use overtime and idle time to meet demand.

Plan 3: Maintain constant work force of 20, and build inventory or incur Stockout cost. The firm must begin January with the 50-unit inventory on hand.

Compare the costs of the three plans in table form.

Solution:

: We must first determine what the production requirements are, as adjusted to include a safety stock of 20 per cent of next month’s forecast. Beginning with a January inventory of 50, each subsequent month’s inventory reflects the difference between the forecast demand and the production requirement of the previous month. See Table 2. The costs of the three plans are shown in Tables 3, 4, and 5.

  Forecast demand Cumulative demand Safety stock @20 per cent forecast Beginning inventory Production requirement (fest. + SS beg. inv.)
January 300 300 60 50 300 + 60 – 50 = 310
February 500 800 100 60 500 + 100 – 60 = 540
March 400 1,200 80 100 400 + 80 – 100 = 380
April 100 1,300 20 80 100 + 20 – 80 = 40
May 200 1,500 40 20 200 + 40 – 20 = 220
June 300 1,800 60 40 300 + 60 – 40 = 320
Table No. 2

January February March April May June Total
1. Production required 310 540 380 40 220 320
2. Production hours Required (1 × 10) 3,100 5,400 3,800 400 2,200 3,200
3. Hours available per Worker at 8/day 176 152 168 168 176 160
4. Number of workers Required (2/3) 18 36 23 3 13 20
5. Number of workers Hired   18     10 7
6. Hiring cost (S × Rs. 300)     Rs. 5,400     Rs. 3,000   Rs. 2,100   Rs. 10,500
7. Number of workers Laid off 2   13 20    
8. Layoff cost (7 × Rs. 400) Rs. 800   Rs. 5,200 Rs. 8,000   Rs. 14,000
Table No. 3 Plan 1(Vary Work-force Size)
21 8 image 1351
Table No. 4 Plan 2 (Use Overtime and Idle Time)

*Incremental cost of OT = overtime cost – regular time cost = Rs. 9 – Rs. 6 = Rs. 3.

21 8 image 1352
Table 5 Plan 3 (Use Inventory and Stockout Based on Constant 20-Worker Force)

Note that plan 3 assumes that a Stockout cost is incurred if safety stock is not maintained at prescribed levels of 20 per cent of forecast. The firm is in effect managing the safety-stock level to yield a specific degree of protection by absorbing the cost of carrying the safety stock as a policy decision.

ed010d383e1f191bdb025d5985cc03fc?s=120&d=mm&r=g

DistPub Team

Distance Publisher (DistPub.com) provide project writing help from year 2007 and provide writing and editing help to hundreds student every year.