AID18763: A software development project was planned to be completed in 12 months. The review of the project after eight months revealed that Rs. 120000 was spent on the project for 48% of project completion. Consider total project budget as Rs 240000. Calculate and explain the schedule and cost performance index for this situation.

 300

Category:

AID18763: A software development project was planned to be completed in 12 months. The review of the project after eight months revealed that Rs. 120000 was spent on the project for 48% of project completion. Consider total project budget as Rs 240000. Calculate and explain the schedule and cost performance index for this situation.